All Saints’ Church Westbere stands on elevated ground overlooking the River Stour on its route into Canterbury. There has been a building on the site since before the Norman Conquest and some fabric survives from these early buildings.
The present building dates from a significant rebuilding in the early 14th century, primarily using pudding stone, which is a post-glacial conglomerate that is not often found in Kent. The church was extensively restored in 1859 and again in 1887, when the Nave was ecased in knapped flintwork and the western bellcote was added.
One of the principal glories of this small two cell church is the roofs. These date from the 14th century, both to the Chancel and the Nave and consist of a series of tie beams with crown posts supporting the collar ties and rafters above.
The church has exhibited signs of structural movement for some time. This manifests itself in the south wall leaning out by as much as 6” from top to bottom both in the Nave and the Chancel, and the tie beams of the roof pulling out of their southern wall bearings. Previous repairs undertaken in part of the Chancel have tried to rectify this movement by the installation of significant steelwork and a tie rod, but these repairs did not fully analyse the reasons for the movement and tried to treat symptoms rather than causes.
On the recommendation of English Heritage, the Parish appointed Thomas Ford & Partners to undertaken a reappraisal of the building and to advise on the best way forward for the building’s consolidation and repair. Early analysis, undertaken jointly with Adrian Cox Structural Engineers, highlighted the fact that the church is built into the side of a significant slope down into the river valley. This means that the north walls are founded in good quality ground, whilst the south wall of the Nave and Chancel are constructed on fill which is inherently weak. The absence of rainwater goods generally on the church and burials in the 18th and 19th century against the church wall have led to the slow washing out of fine material and the undermining of the southern walls, allowing slow but continuing rotation. This has manifested itself over the last 500 years with an outward lean on the southern walls of up to 6”. The roofs were acting as restraint to the outward movement of the walls but clearly this position was deteriorating.
Further investigations into the wall heads revealed that the inner and outer wall plates of both the Nave and the Chancel to both the north and south elevations were completely rotten. The wall plates had originally been built into the walls during the construction of the building and the 19th century restoration had piled further material on top of them, fostering worm and beetle activity. In some cases in the Nave, the entire inner and outer wall plates were completely rotten and in some cases missing, as well as the cleats which bound the two plates together and the base of some rafters were also decayed. This meant the roof could no longer resist the outward rotation of the walls.
These discoveries highlighted the complex issues facing the design team and there was no sense in treating the symptoms of the movement without rectifying the causes. In addition, it was agreed that any works would have no visual impact on the church building, ensure it remained in use throughout the repair project, and retain as much historic fabric within the building.
The first problem to tackle was the rainwater goods and the washing out of fine material adjacent and below the southern wall foundations. This was dealt with by the installation of new rainwater goods and downpipes leading directly into soakaways well away from the church building. These soakaways also had to be constructed above the principal burial layers which, in some cases, were within 1.2 metres of the ground surface and required significant archaeological input to avoid impacting on the archaeologically sensitive material. The installation of rainwater goods means that no further fine material will be washed away from the southern wall and it is hoped that the rotation of the southern wall to the Nave and Chancel will now be stabilised in their present location.
The next problem was to decide how the roof was to be repaired, ensuring that it remained insitu. Analysis of the structure and investigations into the wall head showed that by lifting the lower areas of eaves tiles and removing the 19th century debris, material from the wall heads, the inner and outer wall plates could be exposed without having to dismantle the roof structure, as long as internal scaffolding was designed to take the weight of the roof if necessary. It also became apparent that the wall plates on the Nave, which were built into the walls, could be removed without removing 19th century facing flintwork if the work was carried out from above.
A method was devised which allowed the wall plates to be cut into 2 metre sections to be removed and new English oak wall plate sections inserted in 2 metre sections joined together with stainless steel rods and resin. Whilst this is introducing new construction techniques and joints into the external wall plate, it meant all the rafters, ashlar posts and the roof structure could remain insitu to remove any chance of movement in the historic roofs. The reinstallation of cleats between the inner and outer wall plates and repairs of sections of the inner wall plate meant that the roof structure on the wall heads to both the north and south elevations acted as one, restraining the walls. The reattachment of the principle tie beams again into the wall heads by a mixture of resin repair and new timberwork meant that the southern walls of the Chancel and the Nave could not move any further.
The design team also decided to reinstate and/or replace most of the peg fixings in the Nave and Chancel roofs to ensure these acted as single structures and some of the previous concrete and steelwork was removed, as this was felt not to be benefitting the structure at the present time. Of great interest during the works was the discovery of the original 14th century wall head, which had been carefully plastered before the installation of the wall plates and their building in. This was photographed and is now exposed for a future study.
The project also tackled significant defects in the external walls of All Saints’, primarily the southern wall of the Nave and Chancel, but also buttresses rebuilt in the 14th century and faced by the Victorians. This work required the systematic grouting on a 450mm grid of the southern walls to fill voids, and the removal of recent pointing to allow the walls to breathe. This means that both the southern walls of the Nave and Chancel now act as single structural elements, further stiffening the structure. In addition, buttresses were re-grouted and pinned back to the main body of the building to further enhance structural integrity.
The works were designed so that this small church with a loyal worshipping community could continue to use the building every Sunday. This was felt to be of great pastoral importance. The works were generously grant aided by English Heritage and the principal contractor was WJR Roofing Limited of Beckenham, Kent.
The project overcame significant philosophical repair issues, balancing the removal of historic fabric to stabilise the structure, ensuring as much historic timberwork as possible could be retained and that almost all the repairs are not visible to general view. For a small worshipping community, raising the significant sums involved was a matter of great faith. The church has now been structurally secured and continues to be at the centre of the village of Westbere, both for worship and secular uses.
For more information on the team winning the award please visit the following websites
www.thomasford.co.uk
www.adriancox.co.uk
www.wjrroofing.com
W.Mellor and Mottram
Specialist heating needs of Victorian and medieval churches throughout the UK
W.Mellor and Mottram
Grassform Plant Hire Ltd
Ground Protection and Turf Care Specialists. Enhance and/or maintain the landscape of your historic or heritage site with Grassform’s solutions.
Grassform Plant Hire
Hall & Ensom
Provide a service tailored to your needs including quantity surveying and services engineering. We have over 40 years experience in building surveying
Hall & Ensom Chartered Surveyors
Popular
Latest